28 MW onshore wind in southern Lithuania, ready to build 2028
A 28 MW onshore wind project with a planned 110 kV connection: land control and zoning are complete, the environmental impact assessment is under way and the grid connection is in progress. The smallest in the portfolio and the closest to a single-asset acquisition.
Where the project actually stands
"Ready to build" is a market label, not a legal status – so here is every item and where it stands. Ready to build (target 2028) means: land secured, zoning complete, environmental impact assessment concluded, grid connection agreed and the building permit issued. Today land control and zoning are complete, the environmental impact assessment is under way with completion expected in 2027, and the grid connection is in progress (28 MW at 110 kV potential).
- Land controlComplete
Land agreements signed
- ZoningComplete
Zoning complete
- EnvironmentalIn progress
Environmental impact assessment started, completion expected 2027
- Grid connectionIn progress
In progress – 28 MW at 110 kV potential
- Building permitNot started
Follows the grid connection · ready to build 2028
Grid and capacity
- Planned capacity
- 28 MW
- Voltage
- 110 kV (planned)
- Ready to build
- 2028
- Energisation
- 2029
Site
- Location
- Southern Lithuania
- Land
- Parcels under long-term agreements
- Access
- Existing regional road network
From here to operation
- NowEnvironmental impact assessment
- 2027Environmental assessment completed
- 2028Construction permitting · ready to build
- 2029Energisation
What is in the data room
- Corporate documents of the project company
- Land agreements and parcel register
- Grid connection conditions
- Wind measurement and yield assessment
- Environmental assessment documentation
- Turbine layout and coordinates
- Project timeline
Who to talk to

Our development team handles data room and buyer enquiries for this project.