Contact us
Home / Wind / Wind project – North-Western Lithuania

300 MW onshore wind in north-western Lithuania

A 300 MW onshore wind project with a planned 330 kV connection, in early development: land control is complete, territorial planning and the environmental impact assessment are under way.

300 MWplanned capacity
52wind turbines
330 kVplanned connection
Completeland control
In progressterritorial planning
EIAin progress
Development status

Where the project actually stands

"Ready to build" is a market label, not a legal status – so here is every item and where it stands. This project is in development, not ready to build. Land control is complete; territorial planning and the environmental impact assessment are under way, with completion expected in 2028, and the grid connection is in progress (300 MW at 330 kV potential), followed by construction permitting.

  1. Land controlComplete

    Land agreements signed

  2. ZoningIn progress

    Territorial planning in progress

  3. EnvironmentalIn progress

    Environmental impact assessment started, completion expected 2028

  4. Grid connectionIn progress

    In progress – 300 MW at 330 kV potential

  5. Building permitNot started

    Follows the grid connection

Grid and capacity

Planned capacity
300 MW
Voltage
330 kV (planned)

Site

Location
North-Western Lithuania
Land
Parcels under long-term agreements
Access
Existing regional road network
Timeline

From here to operation

  1. NowEnvironmental impact assessment
  2. 2028Environmental assessment completed
  3. 2029Construction permitting · ready to build
  4. 2029Construction start

What is in the data room

  • Corporate documents of the project company
  • Land agreements and parcel register
  • Grid connection conditions
  • Wind measurement and yield assessment
  • Environmental assessment documentation
  • Turbine layout and coordinates
  • Project timeline

Who to talk to

Energy Unlimited

Our development team handles data room and buyer enquiries for this project.