300 MW onshore wind in north-western Lithuania
A 300 MW onshore wind project with a planned 330 kV connection, in early development: land control is complete, territorial planning and the environmental impact assessment are under way.
Where the project actually stands
"Ready to build" is a market label, not a legal status – so here is every item and where it stands. This project is in development, not ready to build. Land control is complete; territorial planning and the environmental impact assessment are under way, with completion expected in 2028, and the grid connection is in progress (300 MW at 330 kV potential), followed by construction permitting.
- Land controlComplete
Land agreements signed
- ZoningIn progress
Territorial planning in progress
- EnvironmentalIn progress
Environmental impact assessment started, completion expected 2028
- Grid connectionIn progress
In progress – 300 MW at 330 kV potential
- Building permitNot started
Follows the grid connection
Grid and capacity
- Planned capacity
- 300 MW
- Voltage
- 330 kV (planned)
Site
- Location
- North-Western Lithuania
- Land
- Parcels under long-term agreements
- Access
- Existing regional road network
From here to operation
- NowEnvironmental impact assessment
- 2028Environmental assessment completed
- 2029Construction permitting · ready to build
- 2029Construction start
What is in the data room
- Corporate documents of the project company
- Land agreements and parcel register
- Grid connection conditions
- Wind measurement and yield assessment
- Environmental assessment documentation
- Turbine layout and coordinates
- Project timeline