200 MW data center site in a Lithuanian free economic zone, grid conditions secured
Land, grid capacity and permits in one project company, sold ready to build: 200 MW with grid connection conditions secured at 330 kV, on a campus in a free economic zone with 0% corporate tax for 10 years.
What is offered
- Capacity
- 200 MW at 330 kV, grid connection conditions secured
- Land
- Part of the 14.4 ha campus, industrial land use
- Zone
- Free economic zone – 0% corporate tax, 10 yrs
- Grid
- 6.2 km to the 330 kV substation, no reinforcements
- Timeline
- Ready to build 2028 Q1
- Next to it
- 70 MW site with a signed 110 kV grid agreement
- Environmental
- EIA decision expected 2027 Q4
- Structure
- SPV share sale · data room on request
The 200 MW site on the campus
Where the project actually stands
"Ready to build" is a market label, not a legal status – so here is every item and where it stands. Ready to build (target 2028 Q1) means: land secured, 200 MW grid connection agreement signed at 330 kV, EIA decision received and the building permits for the building and the grid connection issued. Today the grid connection conditions are secured and the grid agreement is under way; the EIA decision is expected in 2027 Q4, followed by design and permitting.
- Land controlComplete
Part of the 14.4 ha campus
- ZoningComplete
Industrial land use
- EnvironmentalNot started
EIA decision expected 2027 Q4
- Grid connectionIn progress
200 MW conditions secured at 330 kV · grid agreement under way
- Building permitNot started
Building and grid connection part to follow · ready to build 2028 Q1
Grid and capacity
- Grid conditions secured
- 200 MW at 330 kV
- Distance to substation
- 6.2 km
- Reinforcements
- None required
- Ready to build
- 2028 Q1
Site
- Land
- Part of a 14.4 ha campus, industrial land use
- Height limit
- 30 m
- Zone
- Free economic zone – 0% corporate tax for 10 years
- Access
- Paved road at the site · main highway 4.2 km
- Water
- Underground water access for cooling
- Fiber
- Two separate fibre-optic networks, 2.4 km from the site boundary
- Gas
- Medium-pressure pipeline (up to 5 bar), 0.8 km
- Heat transfer
- Opportunity to supply excess heat to the city district heating network, 3.6 km away (2024: 86 MW average, 277 MW peak heat demand)
From here to operation
- NowGrid connection conditions secured · grid agreement
- 2027 Q4EIA decision
- 2028 Q1Building permits · ready to build
- 2029 Q1Construction and grid connection
What is in the data room
- Corporate documents of the project company
- Land agreements and cadastral extracts
- Zoning and detailed plan decisions
- Grid connection conditions and capacity allocation
- Environmental assessment documentation
- Technical site studies and master plan
- Project timeline
Who to talk to

Our development team handles data room and buyer enquiries for this project.