100 MW data center site in central Lithuania, grid conditions secured

Land, grid capacity and permits in one project company, sold ready to build: 100 MW with grid connection conditions secured at 330 kV, next to a 1 GW pumped-storage hydro plant.

100 MWgrid conditions secured, 330 kV
2027 Q1land-use change
2027 Q2EIA decision
2027 Q4ready to build
2028 Q4grid energisation
0.45 kmto the connection point
Development status

Where the project actually stands

"Ready to build" is a market label, not a legal status – so here is every item and where it stands. Ready to build (target 2027 Q4) means: land secured, land-use change approved, 100 MW grid connection agreement signed at 330 kV, EIA decision received and the building permits for the building and the grid connection issued. Today the land title and the grid connection conditions are secured, the land-use change is in progress and the grid agreement is under way; the EIA decision is expected in 2027 Q2.

  1. Land controlComplete

    Land title secured

  2. ZoningIn progress

    Land-use change in progress

  3. EnvironmentalIn progress

    EIA decision expected 2027 Q2

  4. Grid connectionIn progress

    100 MW conditions secured at 330 kV · grid agreement under way

  5. Building permitNot started

    Building and grid connection part to follow · ready to build 2027 Q4

Grid and capacity

Grid conditions secured
100 MW at 330 kV
Distance to substation
0.45 km
Reinforcements
None required
Ready to build
2027 Q4
Grid energisation
2028 Q4

Site

Land
12.46 ha: 9.5 ha leased for 30 years · 2.96 ha to be purchased
Land use
Change in progress
Height limit
20 m
Access
Paved road at the site · main highway 20 km
Water
Underground water access for cooling
Fiber
Fibre-optic network next to the site
Gas
High-pressure pipeline (up to 25 bar), 1.8 km
Next to it
1 GW pumped-storage hydro plant · PPA or direct-line option
Timeline

From here to operation

  1. NowGrid connection conditions secured · grid agreement
  2. 2027 Q2EIA decision
  3. 2027 Q4Building permits · ready to build
  4. 2028 Q4–2029 Q1Grid connection (Q4) · construction completed (2029 Q1)

What is in the data room

  • Corporate documents of the project company
  • Land agreements and cadastral extracts
  • Zoning and detailed plan decisions
  • Grid connection conditions and capacity allocation
  • Environmental assessment documentation
  • Technical site studies and master plan
  • Project timeline

Who to talk to

Energy Unlimited

Our development team handles data room and buyer enquiries for this project.