Battery storage – Dâmbovița County

7.5 MW / 30 MWh in Dâmbovița County, Romania

7.5 MWpower
30 MWhenergy
3containers
20 kVconnection
0.4 kmto point of connection
2026 Q4ready to build
Project data

What is offered

SPV
Romanian project company
Location
Dâmbovița County, near Târgoviște
Grid
CTS approval 2025-12 · ATR obtained 2026-06
Permitting
All urbanism approvals obtained 2026-08
Building permit
Documentation prepared · expected 2026 Q4
Structure
100% share sale · data room on request
Development status

Where the project actually stands

"Ready to build" is a market label, not a legal status – so here is every item and where it stands. Ready to build (target 2026 Q4) means: land secured, ATR issued, all urbanism approvals obtained in August 2026 and the building permit expected in 2026 Q4.

  1. Land controlComplete

    Superficies agreement signed 2025-06, 30 years

  2. Urbanism certificateComplete

    Obtained 2025-08

  3. Urbanism approvalsComplete

    All obtained 2026-08

  4. Grid connectionComplete

    CTS approval 2025-12 · ATR obtained 2026-06

  5. Building permitIn progress

    Documentation prepared (DTOE, DTAC) · expected 2026 Q4

Grid and capacity

Approved capacity
7.5 MW
Voltage
20 kV
Point of connection
220/110/20 kV substation
Distance to PoC
~0.4 km
Ready to build
2026 Q4
Target COD
2027 Q4

Site

SPV
Romanian project company
Location
Dâmbovița County, Romania
Energy
30 MWh
Storage system
3 containers, MEW 20/3150-3
Inverters
6 units, 1,250 kW
Transformers
3 units, 9.45 MVA
Timeline

From here to operation

  1. 2025Land, urbanism certificate, grid approval
  2. 2026 Q2–Q3ATR and urbanism approvals
  3. 2026 Q4Building permit · ready to build
  4. 2027 Q4Target commercial operation

What is in the data room

  • Corporate documents and shareholding of the SRL
  • Land (superficies) agreement and cadastral documents
  • Urbanism certificate and approvals
  • ATR and grid connection documentation
  • Building permit documentation
  • Technical solution: containers, inverters, transformers
  • Project timeline

Who to talk to

Energy Unlimited

Our development team handles data room and buyer enquiries for this project.