20 MW battery storage project in north-western Lithuania
A 20 MW standalone battery project in the Lithuanian pipeline, developed for connection at transmission level.
20 MWpower
80 MWhenergy
4 hduration
Transmissionconnection level
In progressgrid connection
Development status
Where the project actually stands
"Ready to build" is a market label, not a legal status – so here is every item and where it stands. This project is in development, not ready to build. Land control and zoning are complete and the grid connection at transmission level is in progress; the building permit follows the grid connection.
- Land controlComplete
Land agreement signed
- ZoningComplete
Zoning complete
- Grid connectionIn progress
Grid connection in progress
- Building permitNot started
Follows the grid connection
Grid and capacity
- Planned capacity
- 20 MW
- Connection level
- Transmission
- Region
- North-Western Lithuania
- Status
- See development status above
- Structure
- Share sale of the project company
- Acquisition
- Possible at any stage of development
Site
- Region
- North-Western Lithuania
- Capacity
- 20 MW
- Land
- Land agreement signed
- Terrain
- Agricultural land
- Access
- Existing road network
Timeline
From here to operation
- NowGrid connection
- NextReady to build
- AfterConstruction
What is in the data room
- Corporate documents of the project company
- Land agreements and cadastral extracts
- Zoning documentation
- Grid connection application and conditions
- Technical solution and layout
- Project timeline