24.5 MW / 98 MWh in Ilfov County, 10 km from Bucharest
24.5 MWpower
98 MWhenergy
22containers
110 kVconnection
< 0.1 kmto point of connection
2026 Q3ready to build
Project data
What is offered
- SPV
- Romanian project company
- Location
- Ilfov County, Chitila
- Grid
- ATR obtained 2026-05 · Chitila 110/20 kV substation
- Permitting
- All urbanism approvals obtained
- Building permit
- Obtained 2026-07
- Structure
- 100% share sale · data room on request
Development status
Where the project actually stands
"Ready to build" is a market label, not a legal status – so here is every item and where it stands. Ready to build (2026 Q3): land secured, ATR issued for the full 24.5 MW, all urbanism approvals obtained and the building permit issued in July 2026.
- Land controlComplete
Superficies agreement signed 2024-09, 30 years
- Urbanism certificateComplete
Obtained 2025-07
- Urbanism approvalsComplete
All approvals obtained
- Grid connectionComplete
ATR obtained 2026-05 for 24.5 MW
- Building permitComplete
Obtained 2026-07
Grid and capacity
- ATR capacity
- 24.5 MW – matches the marketed capacity
- Voltage
- 110 kV
- Point of connection
- Chitila 110/20 kV substation
- Distance to PoC
- ~0.1 km
- Ready to build
- 2026 Q3
- Target COD
- 2027 Q4
Site
- SPV
- Romanian project company
- Location
- Ilfov County, Romania – 10 km from Bucharest
- Energy
- 98 MWh
- Storage system
- 22 containers, LUNA2000-4.5 MWh
- Inverters
- 115 units
- Transformers
- 3 units, 27 MVA
Timeline
From here to operation
- 2024 Q3Land agreement
- 2025 Q3Urbanism certificate
- 2026 Q2–Q3ATR and building permit · ready to build
- 2027 Q4Target commercial operation
What is in the data room
- Corporate documents and shareholding of the SRL
- Land (superficies) agreement and cadastral documents
- Urbanism certificate and approvals
- ATR and grid connection documentation
- Building permit documentation
- Technical solution: containers, inverters, transformers
- Project timeline
Who to talk to

Our development team handles data room and buyer enquiries for this project.