Contact us
Home / Battery storage / Battery storage – Ilfov County

Battery storage – Ilfov County

24.5 MW / 98 MWh in Ilfov County, 10 km from Bucharest

24.5 MWpower
98 MWhenergy
22containers
110 kVconnection
< 0.1 kmto point of connection
2026 Q3ready to build
Project data

What is offered

SPV
Romanian project company
Location
Ilfov County, Chitila
Grid
ATR obtained 2026-05 · Chitila 110/20 kV substation
Permitting
All urbanism approvals obtained
Building permit
Obtained 2026-07
Structure
100% share sale · data room on request
Development status

Where the project actually stands

"Ready to build" is a market label, not a legal status – so here is every item and where it stands. Ready to build (2026 Q3): land secured, ATR issued for the full 24.5 MW, all urbanism approvals obtained and the building permit issued in July 2026.

  1. Land controlComplete

    Superficies agreement signed 2024-09, 30 years

  2. Urbanism certificateComplete

    Obtained 2025-07

  3. Urbanism approvalsComplete

    All approvals obtained

  4. Grid connectionComplete

    ATR obtained 2026-05 for 24.5 MW

  5. Building permitComplete

    Obtained 2026-07

Grid and capacity

ATR capacity
24.5 MW – matches the marketed capacity
Voltage
110 kV
Point of connection
Chitila 110/20 kV substation
Distance to PoC
~0.1 km
Ready to build
2026 Q3
Target COD
2027 Q4

Site

SPV
Romanian project company
Location
Ilfov County, Romania – 10 km from Bucharest
Energy
98 MWh
Storage system
22 containers, LUNA2000-4.5 MWh
Inverters
115 units
Transformers
3 units, 27 MVA
Timeline

From here to operation

  1. 2024 Q3Land agreement
  2. 2025 Q3Urbanism certificate
  3. 2026 Q2–Q3ATR and building permit · ready to build
  4. 2027 Q4Target commercial operation

What is in the data room

  • Corporate documents and shareholding of the SRL
  • Land (superficies) agreement and cadastral documents
  • Urbanism certificate and approvals
  • ATR and grid connection documentation
  • Building permit documentation
  • Technical solution: containers, inverters, transformers
  • Project timeline

Who to talk to

Energy Unlimited

Our development team handles data room and buyer enquiries for this project.